Atura Power | Niagara Hydrogen Centre
Canada
FID
Overview
Status
-
FID
Region
-
North America
Geography
-
Canada
State
-
Ontario
Equity Owner
-
Atura Power, a subsidiary of Ontario Power Generation
Proponent
-
Atura Power
Output
-
Green hydrogen
Type of electricty
-
Hydro
Capacity
-
20 MW
Financing
-
Technology
-
Cummins PEM electrolyzer
Technical Advisors
-
CEM Engineering, Sacre-Davey Engineering
Advisors
-
Project Contact
-
Shelley Babin, Atura Power President and CEO
Lawyers
-
Project Cost
-
Offtaker
-
Commercial Operations Date
-
2025
Decommission Date
-
FID
-
December, 2023
Description
The project involves Ontario’s first 20 MW green hydrogen facility.
It will use Cummins’ proton exchange membrane (PEM) electrolysis system will be manufactured at its Mississauga, Ont. facility.
Powered by renewable hydroelectricity, this carbon-free green hydrogen will then be provided to industrial customers for immediate consumption, and transported and blended into the fuel stream at Atura Power’s Halton Hills Generating Station, creating cleaner electricity for Ontario.
A spokesperson for Atura said the project had taken FID as of early 2024, with construction also beginning in early 2024 and operations slated for 2025.