Battelle Memorial Institute will conduct a feasibility study to advance carbon capture and storage in the Southeastern Illinois Basin. The project was selected for CarbonSAFE Phase II: Storage Complex Feasibility, and will perform technical, economic, and community assessments for potential CO2 storage complexes. It’s among 16 projects selected by the U.S. Department of Energy in… Continue reading Battelle Southeastern Illinois Basin CCS
An IGCC power plant. The CO2 would have been sequestered in basalt formations 1.3 miles underground. The project, which was supposed to become operational in 2013, was canceled in 2008 because of trouble obtaining drilling equipment and general delays.
A facility that can capture up to 1,000 tons of CO2 per year. The CO2 will be stored in concrete to fulfill commercial removal purchases. The sequestration is executed through a partnership with CarbonCure Technologies. Buyers of Heirloom’s CO2 removal credits include Microsoft, Stripe, Shopify, and Klarna. Heirloom claims the facility, which was inaugurated on… Continue reading Heirloom DAC California Facility
The potential carbon capture retrofit of unit 4 at the Tanners Creek power plant. The project was canceled in 2014 after a feasibility study due to financial concerns. The Tanners Creek Plant was retired in 2015.
CapCO2 Solutions develops green methanol-producing technology that fits in a shipping crate. The shipping crate can be placed at ethanol plants and use the carbon captured to produce green methanol. 8 to 10 shipping crates would be able to process all the carbon captured at an average ethanol plant, and make green methanol out of… Continue reading CapCO2 | Adkins Green Methanol Pilot Project
The development of a sequestration site in Illinois. Navigator CO2 Ventures pivoted to focus on the sequestration site after it canceled its 1,300-mile pipeline project in the Midwest due to the unpredictable regulatory environment.
NextEra Energy Resources, LLC and Linde are planning to develop an up to $1bn clean hydrogen facility west of Tonopah, in Maricopa County, Arizona. The Gila Hydrogen Facility will be developed by Gila Hydrogen, LLC, a wholly-owned, indirect subsidiary of NextEra Energy, in collaboration with Linde. The companies plan to develop the new facility on… Continue reading Gila Hydrogen Facility
An integrated green hydrogen and ammonia facility of up to 1.2 MMTPA. The Victoria County Navigation District “Port of Victoria” and ACME Greentech Ventures Americas Inc entered into an option agreement to lease a 245-acre site at The Port of Victoria in August 2023. ACME will conduct its due diligence and feasibility studies to develop… Continue reading Port of Victoria/ACME Ammonia Plant
An oxyfuel retrofit of an idled 65-year-old facility in Illinois. The project got a $1 billion award for FutureGen from the American Recovery and Reinvestment Act. This money was formally committed on September 28, 2010, and needed to be spent by September 2015 or it would have been forfeited. The project was coordinated by the… Continue reading FutureGen
The Tenaska Trailblazer Energy Center CCS project received final air quality permits in 2010 and it was set to begin commercial operations in 2014. In June 2013, Tenaska canceled the project.